Main Street Storm Water Inlet and ADA Repair Project

Share Main Street Storm Water Inlet and ADA Repair Project on Facebook Share Main Street Storm Water Inlet and ADA Repair Project on X (formerly Twitter) Share Main Street Storm Water Inlet and ADA Repair Project on Linkedin Email Main Street Storm Water Inlet and ADA Repair Project link

Project Overview

The City of Aspen will be conducting stormwater inlet and ADA ramp repairs along Main Street between 1st Street and 6th Street beginning July 27, 2026. Construction is anticipated to continue through early October.

This project is part of the city's ongoing commitment to maintaining safe, reliable, and resilient public infrastructure. By repairing aging stormwater inlets and improving ADA ramps, the city is investing in the long-term health of its stormwater system while enhancing accessibility for pedestrians.


Construction Schedule

Crews will work at each location for approximately two weeks, beginning at 6th Street and progressing west toward 1st Street. Work will move block by block as each location is completed.


What to Expect

  • During construction, the following impacts are anticipated:
  • Rolling single-lane closures along Main Street
  • Work occurring at one stormwater inlet location at a time
  • Rolling sidewalk closures around active work areas
  • Temporary parking restrictions, with select spaces in the north and south parking lanes reserved for construction activities
  • Alley access will remain open throughout the project

Motorists, pedestrians, and cyclists are encouraged to use caution when traveling through work zones and follow all posted traffic control signage.


Project Benefits

These repairs will:

  • Improve the reliability and resiliency of the city's stormwater infrastructure
  • Maintain safe and functional drainage systems
  • Enhance pedestrian accessibility through ADA-compliant ramp improvements
  • Help preserve public infrastructure and reduce future maintenance needs
  • Stay Informed


Construction schedules are weather dependent and subject to change.


If you have questions or would like additional information, please contact the project team.

Project Overview

The City of Aspen will be conducting stormwater inlet and ADA ramp repairs along Main Street between 1st Street and 6th Street beginning July 27, 2026. Construction is anticipated to continue through early October.

This project is part of the city's ongoing commitment to maintaining safe, reliable, and resilient public infrastructure. By repairing aging stormwater inlets and improving ADA ramps, the city is investing in the long-term health of its stormwater system while enhancing accessibility for pedestrians.


Construction Schedule

Crews will work at each location for approximately two weeks, beginning at 6th Street and progressing west toward 1st Street. Work will move block by block as each location is completed.


What to Expect

  • During construction, the following impacts are anticipated:
  • Rolling single-lane closures along Main Street
  • Work occurring at one stormwater inlet location at a time
  • Rolling sidewalk closures around active work areas
  • Temporary parking restrictions, with select spaces in the north and south parking lanes reserved for construction activities
  • Alley access will remain open throughout the project

Motorists, pedestrians, and cyclists are encouraged to use caution when traveling through work zones and follow all posted traffic control signage.


Project Benefits

These repairs will:

  • Improve the reliability and resiliency of the city's stormwater infrastructure
  • Maintain safe and functional drainage systems
  • Enhance pedestrian accessibility through ADA-compliant ramp improvements
  • Help preserve public infrastructure and reduce future maintenance needs
  • Stay Informed


Construction schedules are weather dependent and subject to change.


If you have questions or would like additional information, please contact the project team.

Page last updated: 23 Jul 2026, 09:14 AM